The Supreme Court of India restored a dredging contractor’s arbitral award against the Kolkata port, setting aside a Calcutta High Court judgment that had cut it by half and reduced interest to 6%.
The Supreme Court has held that a court hearing an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 cannot modify an arbitral award only because the amount awarded for additional work looks excessive against the value of the original contract. [Marino Dredgeco Limited v. Board of Trustees of the Port of Kolkata, 2026-juristway.com-3721-SC-INDLAW]
Justice K. Vinod Chandran authored the judgment for a Bench that included Justice J.B. Pardiwala. The Court decided two appeals, one by the contractor and one by the port trust, against a judgment of a Division Bench of the Calcutta High Court.
The contract was for dredging an approach channel and basin for a shore-based pilot station at Sagar Island. For the original work, ₹2,79,32,865 of the ₹2,86,56,200 payable had been paid. The arbitration concerned additional re-dredging, which the contractor attributed to siltation, force majeure weather and soil conditions that did not match the data supplied by the port trust. The arbitrator made an award on 3 Nov 2003, and a Single Judge affirmed it under Section 34.
The Division Bench recorded that the award was not based on no evidence, and was neither perverse nor patently illegal. It nevertheless reduced the amount to 50% and the interest to 6% on the principal from 8 Feb 2002, because the claim for additional work exceeded 70% of the original contract, which it said shocked its conscience.
The contractor relied on Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited (2025 INSC 605) to argue that the power of interference was limited. The port trust sought to have the entire award set aside, contending that no completion certificate was issued and no additional work was entrusted, and alternatively asked that the 50% reduction be retained.
The Court held that the test of an award shocking the conscience, which applies to a conflict with the most basic notions of morality or justice, is “not to be applied on a mere lip service” and needs a substantive reason. The Division Bench had not examined the measurements or invoices, and doing so would in any event be an adjudication on merits that the Act prohibits. The re-dredging was of the same nature as the original work, and the quantification could not be split into valid and invalid parts.
Citing Pam Developments Private Ltd. v. State of West Bengal (2019), the Court added that an award cannot be disturbed merely because the award debtor is a Government entity and the amount appears excessive. The contractor’s appeal was allowed and the arbitral award restored. The port trust’s appeal was disposed of.